Palisades Fire Impact Area Update

Teammates,

It’s been a great week of progress for debris removal in the area impacted by the Palisades Fire.

We removed over 70,000 tons of debris this past week and are currently operating 102 debris removal crews throughout the area. Our 5-day average for clearing sites is 44 per day, and to date we have cleared over 2,887 properties of our anticipated workload of about 4,500 parcels. By the end of May, we anticipate clearing all opt-in properties along PCH and more than 70% of our total expected workload across the Palisades Fire impact area.

Key numbers:

Weekly Progress:

MAJ Grussing or I will send an update the same time next week. If you have questions or concerns, please do not hesitate to reach out.

LA, Malibu, Palisades Strong!

Respectfully,

COL Jeffrey S. Palazzini
Colonel, Engineer
United States Army Corps of Engineers
Emergency Field Office Commander
Palisades Fire